Construction
project at Yosemite High School continues
—
Earlene Ward

This current music/drama building
will be turned into a 400-seat performing arts center after renovation work is
completed. The “no frills” facility will cost between $750,000 and $850,000.
by Earlene Ward - Yosemite High
School
The construction project at Yosemite High School, funded by
a bond measure passed by voters in 1998, is continuing at the site.
“We are extremely pleased with the project and the many
positive changes we have been able to make at the site,” says Yosemite Joint
Union High School District Superintendent Bill McCabe.
During the summer, the older parking lots were re-paved,
fencing was added to more of the campus, excavation was done for baseball
fields, and preliminary work was started for a music classroom building. An
additional portable classroom was added at the Evergreen High School campus.
A citizen committee is working with the district to raise
funds to put in a community swimming pool complex at the high school.
“We have raised about half of the funds needed to complete
the pool complex,” Mr. McCabe says. “We will be seeking donations and grants to
finish the project.” He says the pool would be available to the public during
non-school hours.
Mr. McCabe says the goal is to break ground on the $2.4
million project in June 2003. Anyone wishing to make a donation to the project
can send a check to El Capitan Foundation Swimming Pool Fund, Post Office Box
2221, Oakhurst 93644.
Music building, roofs
The 60-day bid process has begun for the two-room music
classroom building. Mr. McCabe expects construction to start in February or
March with the building ready for students in the fall of 2003.
When the new classroom building is complete, work will start
to renovate the current music/drama classroom building.
This building will be turned into a 400-seat performing arts
center. Mr. McCabe says the “no frills” facility will cost between $750,000 and
$850,000.
With help from a Federal Renovation Grant, the school will
replace the original, 25-year-old roofs on the buildings.
Mr. McCabe says they will be replacing the wooden-shake
roofs with fire-resistant materials.
An additional cost for the roof replacements will be removal
of the asbestos in the original roofs. “This will add about $15,000 to each
building we re-roof,” Mr. McCabe says.
District staff is searching for grant funds that may help
with this added expense. Funds for the re-roofing project will come from
developer fees, deferred maintenance funds and grants.
Bond election
Mr. McCabe is anxiously awaiting the results of the state
bond election in November. When a state bond is passed, the district will be in
line to receive $1 million in state matching funds for the bond project.
“When we passed our $11.76 million bond in 1998, the state
was matching 100 percent, therefore we promised the voters a $23 million
project.
However, that changed within a few months to a 50 percent
match and then changed again to a priority point system,” Mr. McCabe explains.
“Under the priority point system, we will not receive any
more matching funds from the state unless a state bond passes.
“We are so low on the priority point list that money will
not be available without a state bond,” he says.
He adds that the Los Angeles Unified School District
receives the majority of the state funds now under the point system.
To date, YHS has received $3.5 million from the state and is
owed $1 million more.
Original goals
Mr. McCabe points out that a lot of progress has been made
toward meeting the original goals of the bond.
As stated in the Sample Ballot and Voter Information
Pamphlet at the time of the election, the projects to be accomplished with the
bond funds were: Convert open-space classrooms into conventional classrooms;
build additional classrooms; build an auditorium; expand the library/media
center and extend technology campus-wide; build a cafeteria to allow the campus
to be closed; add more parking and more recreational facilities.
Highest priorities
“One of the highest priorities for the public, when we were
working on the bond measure, was that the campus be closed at lunchtime,” Mr.
McCabe recalls.
“Therefore, the construction of a cafeteria/multi-purpose
room was our first new building because we could not close the campus until we
had a facility to feed all of the students.
“We closed the campus to all students but seniors starting
in the fall of 2001 and this has worked very well.”
YHS Principal Steve Raupp said closing the campus went so
smoothly there were no complaints from the community.
“I commend the staff on how professional they were in taking
on this huge task of closing the campus,” Mr. McCabe says. “It all worked
beautifully.”
Remodeling
Renovation of the original open-space classrooms was also a
high priority. “All of the original buildings but two have been remodeled,” Mr.
McCabe says and those two will be remodeled in the near future.
One of the original open-space buildings was turned into a
state-of-the-art library / media center that includes a 30-station computer lab
plus additional computer work stations in the main part of the library.
Another original building was renovated to become science
classrooms and laboratories. The shop building was remodeled into individual
rooms for welding, auto and woodworking classes.
The front building on the campus was converted into an
administration building for the district office and YHS. Mr. McCabe says the
front building was chosen as the administration building as a user-friendly
approach for parents and the community.
In the past, the YHS administration office was in the middle
of the campus and the district office was at the far end of the campus. “You
almost needed a hunting permit to find them,” he says.
The last two buildings to be converted are the performing
arts classroom building that will be turned into a performing arts center
beginning in the fall of 2003 after new music classrooms are completed and the
building that houses home economics and art which will be converted as soon as
funds are available.
Plans have been drawn for new permanent classrooms on the
campus. When the district receives the $1 million the state owes it at this
time, it will go toward construction of the permanent classrooms.
Technology, too
Great strides have been made, Mr. McCabe says, in expanding
technology throughout the district. Thanks to a number of grants over the past
four years, there is at least one computer in every classroom. There is a 4.75
to one student to computer ratio and there are six full computer labs on
campus. A fiber optic backbone that connects the entire campus was put in with
bond funds.
A large new parking lot has been added, including two
bridges for access. Work is underway to build new baseball fields and the
tennis courts have been resurfaced. Locker rooms were remodeled and enlarged in
the school's gymnasium. This project included increasing the locker room
capacity by 50 percent, adding a team room, trainer's facility and storage
areas.
“Our plans to construct a new performing arts center had to
be scaled back because of the state funding, but we believe the 400-seat center
that we now have planned will be adequate for many years,” Mr. McCabe says.
Additional projects have included a greenhouse, fencing and
roads at the agriculture farm; areas for record storage; exterior lighting
around the campus; and fencing of almost the entire 95-acre campus.
“We have worked hard to complete the projects that have the
biggest impact on student safety and a positive learning environment.
“If we receive the million dollars from the state, and as we
accumulate developer-fee money, we will continue to work on the project,” Mr.
McCabe concludes.