Use money for smaller projects, say YHS trustees

by Lacey Rees

of the Sierra Star

Still reluctant to commit to borrowing money to finish Yose­mite High School’s construction projects, the district’s Board of Trustees moved to use existing funds to begin work on some of the items on its new priority list.

As the money is spent, the trustees will later decide how much borrowed money will be needed to finish all the projects.

The top four items on the construction list — remodeling Buildings 700 [drama] and 300 [art, home economics], building separate band and chorus classrooms plus six other classrooms, all long-term projects — will go into the design phase.

It will take up to eight months to get the blueprints of the designs and to wend their way through the state Architect’s Office, said Bill McCabe, Yose­mite High School District su­per­intendent.

In the interim, smaller projects — reroofing the gym, installing a public address system, improving the agriculture facility [fencing and a hot house] and placing basketball hoops in the new gym — will be tackled and completed.

In addition, a new well, the school’s third, has to be drilled, as YHS is presently operating on one well. A second has never been a good producer and is now shut down for recovery during the winter. The school needs a back-up system.

Also on the list, but not to be worked on this time, are five new portable classrooms, reroofing of all the older buildings, parking, sewer lines, and renovating baseball and softball fields. 

 

$2.7 million to spend

There is $2.7 million available to complete short-term projects, says Mr. McCabe. Any money needs beyond that will require a loan.

Trustee David Hartesvelt queried Mr. McCabe why there was now $2.7 million in the construction fund when there was only $1.7 two weeks ago.

The superintendent said now that the year-end budget figures have been finalized, the construction fund gained money from developer fees, money left over from the original bond passed in 1998 and a certificate of deposit. This totaled $3 million. From that was deducted the cost of the energy project, mitigating the wetlands and renovation of Building 500 [shop classes]. That left $2.7 million.

 

5-year loan payoff

Noting that the board was not willing to borrow $3.5 million, Mr. McCabe presented a plan to pay back, in five years, a loan of $1.5 million that will be needed to complete all the projects on the construction list.

Using the increased income in developer fees (approved two weeks ago) the loan payoff would also be contingent on passage of a state bond scheduled for 2003. From that, the district would get $1,185,000 in modernization monies owed by the state.

He said that YHS “is in the middle of the pack” to receive the modernization money that it has coming from the state.

“If the state bond doesn’t pass,” he said, “we will pay $100,000 a year for 30 years” to pay off the loan.

He said that the school could wait for another year before actually applying for the loan.

Mr. McCabe noted that the “big missing ingredient [from the construction list] is the swimming pool. It is more than what people are willing to take on as a debt burden,” he said.

 

No go on pool, fields

Tony Misner, YHS teacher, who previously called himself “one-note Tony” for his advocacy of the swimming pool, said, “I will change my pitch.  The pool is unrealistic.” He asked the board, however, that the pool be put on the next priority list with the hope that there would be a pool at the high school before his son, now in the first grade, becomes a freshman.

Announcing he was wearing three hats, YHS photo/media teacher Larry Pesetski lauded the plans to modify building 700 for performing arts.

Wearing his softball hat, he said that the condition of the baseball and softball fields have been a “constant problem” be­cause of overuse. They have trouble recovering and “it is a safety hazard.” The fields are not scheduled for immediate work.

Mr. Pesetski suggested that if the fields were in better condition, the school could run tournaments and make $65,000 to $75,000, thus “creating a source of revenue for the whole athletic program.”

He said he has had phone calls from parents who thought the new fields were in progress, and he asked that they be kept on the priority list.

He questioned why the school was paying $100,000 to mitigate the wetlands “if you are not going to do something about it. I want to hear where we are on our wetland mitigation with the Army Corps of Engineers,” he asked.

The school is committed to the wetlands project, and “realistically, we are looking at spring,” said Mr. McCabe. “We are moving as quickly as the Corps of Engineers can move.”

 

Hoops and roofs

As a basketball coach, Mr. Pesetski was concerned as to when the basketball hoops would be installed in the new gym. Season practice will begin at the beginning of November.

For this the board had a positive answer. The standards have been ordered, said Buddy Cudd, consultant for maintenance, operations and transportation., and will be installed at the school break at the end of October.

Mr. Cudd also said that the gym needs to be reroofed. After spending $17,000 to redo the gym floor, “the floor can’t take any water,” he says.

The old roof has been in use for 20 years. The plan is to put on a 5-layer hot-mop composition roof, which should last another 20 years. That job will also be done at the October break.

Putting on a metal roof was briefly discussed. Although such a roof would last 100 years, it would cost $90,000, which the school cannot afford.

Eventually all the roofs on the original buildings will have to be replaced. An overhang outside the gym is also set to be covered to keep those attending games dry during inclement weather and to protect the gym floor from water carried in on clothing.

 

Borrow or not

Again Mr. McCabe asked the board if they wanted to borrow.

“I was not comfortable with the loan and I’m still not,” said board member Tom Allcock.

“Interest rates are as low as they will ever be,” said Earlene Ward, grant writer for the district. “If we are feeling we are going to [borrow,] we have to start. Go for the loan.”

“I would like to see us move forward and bring us to closure,” said teacher Randy Haggard.